15-Session Programme · 25 Minutes Per Day · Free · For leaders in Nigerian crude, petroleum-products and gas trading
WEEK 2 OF 3 · CRUDE, PRODUCTS, GAS AND PHYSICAL EXECUTION · SESSIONS 6–10 · WORK AT YOUR OWN PACE
This week’s assessments: Pop Quiz 2 — Contracts, Crude Pricing and the Delivered Margin after Session 8 · Practice Exam 2 — Crude, Products, Gas and Physical Execution after Session 10
By Session 15: you hold a signed 90-Day AI Trading Plan for your own company · Every assignment marked against a published rubric · Pass mark 70
Part Two · Evidence and IntelligenceSESSION 6
The Contract Copilot
Session 6 of 15 · 25-Minute Module

Why This Matters

In Session 5 you asked what your decision needs to know about the future. Today you ask what it has already promised. Every pricing date, tolerance, notice period and payment condition behind your live decision sits in a contract, and a contract assistant can now read that contract faster than any analyst. Speed is not the risk. The risk is a fluent answer drawn from the wrong version, an exception left out, or a delivery term read as if it settled title. A contract copilot is useful when its omissions are measured as carefully as its answers. By the end you will know what it must extract, what it must never infer, and who accepts its work before a number moves.

25-Minute Module
5:00 – 10:00
Version and access before fluency
  • Filter documents before retrieval by authorised user, entity, trade, accepted status and relevant period. A draft with a better filename should not outrank the accepted agreement.
  • The reviewer should see the extracted field, its exact evidence location, any competing clauses and any unresolved qualification. A fluent paragraph with a confidence score is insufficient when it changes a pricing date or payment condition.
  • IN THE PHYSICAL VIEW · THE WORKED CASE
    • Physical view. A fictional product importer's operations team plans receipt against the quantity tolerance and delivery window the assistant extracted from the signed agreement. A later executed amendment changed the window, and retrieval did not bring it back. The receiving plan now rests on a superseded term.
    IN THE COMMERCIAL, RISK AND CASH VIEWS · THE PARALLEL
    • Commercial, risk and cash. The same omission reaches the pricing window, the exposure risk measures and the payment date treasury funds against. Four views each look consistent and all disagree with the contract. The explanation Session 3 demands is a version failure, not a market move.
  • Session 4's point applies: an amendment's printed date can precede its receipt or acceptance. Use the evidence of acceptance.
When an answer is fluent, ask which version it read.
14:00 – 20:00
Measure omissions, and know the stack
  • Build an expert-reviewed reference set covering clean scans, poor scans, amendments, tables, exceptions and missing clauses, plus the hard cases: negative clauses, alternative pricing windows, handwritten amendments, contradictory dates and instructions hidden in attachments.
  • Score critical fields separately. An overall extraction accuracy of 98% can conceal systematic error in the 2% of fields governing claims deadlines. Ninety-nine correct descriptive fields cannot compensate for one wrong beneficiary or pricing basis.
  • StageWhat it doesWhat a leader asks
    Optical character recognitionExtracts text and page coordinates from scanned documentsCan the reviewer open the cited page?
    Schema-constrained extractorProposes fields such as product, quantity basis, pricing window, due date and amendment referenceAre critical fields scored separately?
    RetrievalFinds the relevant accepted evidence the user is permitted to seeDid all material evidence appear among the retrieved passages?
    Language modelDrafts an explanation from that evidenceAre omitted obligations scored?
    Deterministic calculation serviceComputes the price or deadline under an approved specificationIs the arithmetic reproducible?
  • For retrieval, compare keyword search, sentence embeddings that match meaning rather than words, and a hybrid. Sentence-BERT (Reimers and Gurevych, 2019) is a published embedding architecture; it supports the approach, not correct reading of your documents. Exact cargo references and clause numbers often reward keywords; paraphrased obligations can reward meaning. Chunk by clause and keep the amendment hierarchy and cross-references.
  • A self-reported language-model confidence is not a calibrated probability of correctness. Selective prediction research (Geifman and El-Yaniv, 2017) treats abstention as a risk-versus-coverage trade-off; here that means an explicit review route for uncertainty. If an amendment is missing, the correct output can be an incomplete answer naming the missing evidence. A plausible but invented document identifier is a failure even if the sentence is correct.
Ask for the critical-field error before the overall accuracy figure.
Key Terms

Retrieval-augmented generation

A language model that writes from evidence a search has retrieved. It supports grounding, not a guarantee of correct interpretation.

Abstention

A deliberate refusal to answer when evidence is insufficient, routed to a reviewer with enough context to finish the task.

Self-Check — Before You Submit
1. A fictional crude exporter's contract copilot reports 98% overall extraction accuracy. The detail shows its errors cluster in claims deadlines. What should the head of commercial do?
  • A. Approve it, because 98% is high
  • B. Score critical fields separately and hold approval until claims deadlines meet their own standard
  • C. Ask for a confidence score on every field
  • D. Replace the poor scans in the reference set with clean ones
B. Score critical fields separately and hold approval until claims deadlines meet their own standard — An overall 98% can conceal systematic error in the 2% of fields governing claims deadlines. A per-field confidence is tempting, but a self-reported confidence is not a calibrated probability.
2. What does ICC's Introduction to Incoterms 2020 say about title?
  • A. Title passes when risk passes
  • B. The delivery term fixes when title passes
  • C. The rules cover title and payment together
  • D. The rules distinguish delivery, risk and costs and do not determine transfer of title
D. The rules distinguish delivery, risk and costs and do not determine transfer of title — The rules do not determine transfer of title and exclude payment terms and other sale-contract matters. The tempting error is to read ownership from a three-letter delivery term; the assistant must extract the actual title provisions.
3. In evaluation, the copilot cites a document identifier that does not exist, but the sentence it supports is correct. How is that scored?
  • A. As a pass, because the sentence is right
  • B. As a minor formatting issue
  • C. As a failure
  • D. As a pass if the stated confidence was high
C. As a failure — The reviewer must be able to open the cited page and see the supporting passage. Generating a plausible identifier is a failure even when the sentence happens to be correct, because the next one may not be.

Today’s Assignment

Write Section 6 of your plan: the contract terms your Session 1 decision depends on and the contract-to-trade acceptance record that governs them.
  • List the terms your decision depends on in your company: pricing basis, quantity tolerance, delivery, payment, title, documentation, notice periods and claims conditions. Mark any that do not apply and say why.
  • Say where each lives, which version is accepted and who may access it.
  • Name the critical fields that must be scored separately, and the hard cases a reference set drawn from your own documents must include.
  • Design the acceptance record: the fields stored, the commercial, legal and operations reviewers by role, and the point at which the price engine is called.
  • State what the copilot may never do in your business.
  • The honest part: where your company relies on someone's memory of a contract, or lets a delivery term stand in for title. Describe structure; no confidential terms, prices, counterparty names or bank details. If no AI is in use yet, that is normal; the first step may be a reviewed extraction template. Aim for 400 to 900 words.
YOUR 90-DAY PLAN

Section 6 — The contract terms our decision depends on and the contract-to-trade acceptance record.

How this is marked — the rubric
Lists the decision's terms with location, accepted version and access rules for each25
Names critical fields scored separately and hard cases drawn from the company's own documents25
Designs an acceptance record with reviewers by role and the point the price engine is called30
States what the copilot may never do and gives an honest example from the company20
Total · pass mark 70100
Submitting session 6
Write your answer in Word or Google Docs. The first line must read Session: 6, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
Capabilities Covered
Contract extraction disciplineVersion and access controlTitle versus delivery termsCritical-field evaluationAcceptance before calculation
Tick it once you have submitted.Next: Session 7 →
Part Three · Crude and Petroleum ProductsSESSION 7
Crude Pricing, Differential Exposure and Cargo Quality
Session 7 of 15 · 25-Minute Module

Why This Matters

Session 6 secured the terms. Today you follow the price those terms create and the quality that decides whether the cargo is worth buying. A crude price is rarely one number: it is a formula that keeps moving until its last pricing day, and a cheap cargo can be expensive to use. If your business trades gas or serves the trade from treasury, credit or legal, apply this to the nearest equivalent decision or to the counterpart you depend on. Price is a formula with a clock; quality is a measurement with an evidence chain. AI can sharpen both comparisons. It cannot fix a price with hindsight or release a cargo.

25-Minute Module
6:00 – 11:00
Compare on the same basis
  • Netback is what a sale is worth back at your starting point after differential, freight, insurance, handling, quality adjustments, financing and other applicable costs. Compare at the same valuation time and quantity basis, keeping confirmed costs apart from estimates.
  • Assumed teaching prices, 500,000 barrelsDestination ADestination B
    Price per barrel$80.00$81.20
    Transport$2.00$3.10
    Handling$0.40$0.60
    Netback before other costs$77.60$77.50
    Difference across the cargo$0.10 × 500,000 = $50,000 to AReversed by any extra financing or delay cost above $50,000
  • AI may estimate destination demand, congestion or differential behaviour; the executive should see the binding constraint and the assumption most likely to reverse the decision. Do not extrapolate a grade relationship merely because two crudes are both described as light; where history is sparse, use bounded scenarios and say so.
  • THE DOCTRINE

    Reconcile forecast and realised netback by price, differential, freight, delay, quality and financing. Distinguish an improved decision from a market move that would have benefited the baseline strategy as well.

A small netback advantage is one cost line away from reversing. Ask which line.
15:00 – 21:00
A cheap cargo can be expensive to use
  • Crude value depends on the buyer's facilities, feedstock range, yields and constraints; product value on specification, contamination history, handling and permitted sale channels. The US Energy Information Administration explains that crude characteristics and refining processes affect outputs; that does not supply a Nigerian refinery's yield model.
  • IN THE PHYSICAL VIEW · THE WORKED CASE
    • Physical view. Record sample identity, sampling basis, laboratory method, result, certificate, batch and release authority. A quality prediction should not overwrite an accepted test result. A suspicious certificate triggers verification with the issuer, not a synthetic replacement generated to complete the pack.
    IN THE COMMERCIAL, RISK AND CASH VIEWS · THE PARALLEL
    • Commercial, risk and cash. A model of refinery economics is not automatically a model of trading resale value; for a merchant trader, accepted buyer bids and contractual penalties may be the target. Predict yield, energy cost, quality penalty and uncertainty separately so the commercial owner can challenge each.
  • A teaching blend: component A carries an assumed 10 units of a property, B carries 30. A 50:50 blend by mass gives 20 under a linear mixing assumption; against a limit of 18, B may be at most 0.40. Some properties mix nonlinearly, so this does not establish that a real fuel is acceptable.
  • THE DOCTRINE

    A fast surrogate does not certify compatibility, quality or safe processing. AI can suggest candidates for evaluation while the laboratory and technical authorities control acceptance.

  • A surrogate is a fast model imitating a slower process or economics model over a stated range. Candidates the book names include regularised regression, gradient-boosted trees and a Gaussian-process surrogate for small, carefully defined datasets. A buyer's reported yield can reflect configuration and operating choices as well as crude quality.
Ask which number on the quality screen was measured and which was predicted.
Key Terms

Netback

The value of a sale back at the starting point after differential, freight, insurance, handling, quality, financing and other applicable costs, on the same valuation time and quantity basis.

Domain of use

The documented range of inputs and operating conditions over which a surrogate has been tested. Outside it, results go to physical review.

Self-Check — Before You Submit
1. In the book's fictional five-day, equally weighted pricing window on 100,000 barrels, three days are fixed. If only the two open daily prices each rise $1, what happens to purchase cost?
  • A. It rises $100,000
  • B. It rises $40,000
  • C. It rises $20,000
  • D. It is unchanged, because the cargo is physically fixed
B. It rises $40,000 — Two of five days moving $1 raises the average $0.40, or $40,000 on 100,000 barrels. The tempting $100,000 treats the whole price as open.
2. A vendor's price-fixing adviser shows strong backtested gains. What is the first question to ask?
  • A. Did the optimiser use only information observable when each fixing action was taken?
  • B. How often did the model guess the next day's direction?
  • C. Can the model fix the whole window at once?
  • D. Was it trained on a neural network?
A. Did the optimiser use only information observable when each fixing action was taken? — A simulation that sees the full future window will overstate value. Direction-guessing is the tempting measure, but the book's measure is incremental realised contribution and its downside against a permitted neutral policy.
3. A fictional refinery offtaker's blend optimiser proposes a high-margin blend near the edge of its surrogate's training evidence, with almost no specification slack. What should the head of trading do?
  • A. Approve it, since the surrogate predicts it is within limits
  • B. Widen the specification limit to create slack
  • C. Retrain the surrogate using the recommended blend
  • D. Send it to physical review and compare it with a lower-margin candidate that survives realistic uncertainty
D. Send it to physical review and compare it with a lower-margin candidate that survives realistic uncertainty — Optimisers find where a surrogate is least trustworthy. Approving on the prediction is the trap: model feasibility and physical certification are distinct decisions.

Today’s Assignment

Write Section 7 of your plan: the price formula behind your Session 1 decision with its clock, the same-basis comparison and the quality evidence the decision needs.
  • Write the price formula behind your decision in your company, or its nearest equivalent, with every pricing day, weight and adjustment, and the latest time each portion can change.
  • Show the fixed and unfixed portions and the open sensitivity on numbers labelled assumed; no confidential prices.
  • Compare the alternatives on the same valuation time and quantity basis, and name the assumption most likely to reverse the decision.
  • Set out which quality properties determine rejection, which may be predicted and which must be measured, the evidence chain to release authority, and any model's domain of use.
  • The honest part: where your company has credited a favourable market move to a decision, or treated a predicted quality as measured. If no AI is in use yet, that is normal; the first need may be a controlled formula engine. Aim for 400 to 900 words.
YOUR 90-DAY PLAN

Section 7 — Our price formula and its clock, the same-basis comparison and the quality evidence our decision needs.

How this is marked — the rubric
Writes the formula with its clock, fixed and unfixed portions and the open sensitivity, numbers labelled assumed30
Compares alternatives on the same valuation time and quantity basis and names the reversing assumption25
Separates rejection properties into predicted and measured, with the evidence chain and release authority25
States a domain of use for any model and gives an honest example from the company20
Total · pass mark 70100
Submitting session 7
Write your answer in Word or Google Docs. The first line must read Session: 7, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
Capabilities Covered
Price formula disciplineUnfixed exposureSame-basis netback comparisonQuality evidence chainSurrogate boundaries
Tick it once you have submitted.Next: Session 8 →
Part Three · Crude and Petroleum ProductsSESSION 8
The Delivered Margin and Inventory Allocation
Session 8 of 15 · 25-Minute Module

Why This Matters

Session 7 priced the cargo. Today you ask what it actually earns once it is delivered, funded and sold from stock that is genuinely available. A comfortable price spread can disappear in one movement of the sale price, a currency you have not yet bought can change the conclusion, and a positive stock balance can describe product you cannot sell. The useful economic unit is the actual accepted delivery, with a consistent quantity basis and a complete cost boundary. If your business does not distribute products, apply this to the nearest equivalent economic unit you use. Pop Quiz 2 opens at the end of the session.

25-Minute Module
6:00 – 10:00
Funding currency changes the conclusion
  • Suppose the same $7.45 million cost must be acquired at an assumed ₦1,500 per dollar: it becomes ₦11.175 billion. At an assumed ₦1,650 it becomes ₦12.2925 billion, an increase of ₦1.1175 billion before other effects. These are teaching assumptions, not current exchange rates.
  • The exposure depends on what has already been funded or hedged and when naira receipts are obtained. Treasury should distinguish currency purchases, settlement dates, contractual pricing adjustments and remaining exposure.
  • THE DOCTRINE

    Do not translate the whole transaction at a single convenient closing rate and call the difference trading performance.

  • Management review shows expected contribution, downside contribution, peak funding and unresolved conditions together, so a high-margin but cash-intensive cargo can be compared with a smaller executable alternative. The decision record keeps the declined option and the reason, allowing later review without hindsight rewriting.
Ask which part of the dollar cost is still unbought, and when the naira arrives.
15:00 – 20:00
Available stock is a governed state
  • Physical stock, owned stock, released stock and uncommitted stock can differ. Before allocation, reconcile title, batch quality, storage restrictions, existing commitments and movement capability.
  • IN THE PHYSICAL VIEW · THE WORKED CASE
    • Physical view. A fictional distributor's depot shows a high tank reading. Part of the product is on quality hold and part is reserved for an existing commitment. A positive ERP balance alone does not establish saleable availability.
    IN THE COMMERCIAL, RISK AND CASH VIEWS · THE PARALLEL
    • Commercial, risk and cash. The allocation must also respect each customer's accepted demand and credit capacity, firm supply obligations and funding. A plan that sells held stock or extends unsupported credit is a mathematical optimum with no commercial standing.
  • Assumed: 1,500 tonnes, two customers each wanting 1,000Customer A at $30 per tonneCustomer B at $20 per tonneContribution
    Favour A1,000 tonnes500 tonnes$40,000
    Equal split750 tonnes750 tonnes$37,500
  • The apparent $2,500 improvement may disappear if the first allocation breaches a firm supply obligation or creates an unsupported credit exposure. Classify every constraint as mandatory, contractual, operational or discretionary. A discretionary service preference can be traded against contribution within authority.
  • THE DOCTRINE

    A safety restriction cannot become a soft preference because the solver otherwise fails.

  • Storage value is net of storage, financing, loss exposure, quality deterioration and opportunity cost. A forecast price rise alone does not establish a feasible storage arbitrage.
Ask which stock you could sell this afternoon, and who would sign for it.
Key Terms

Delivered margin

Contribution on the actual accepted delivery, with a consistent quantity basis and a complete cost boundary, before items explicitly excluded.

Constraint classes

Mandatory, contractual, operational or discretionary. A discretionary service preference can be traded against contribution within authority; a safety restriction cannot become a soft preference.

Self-Check — Before You Submit
1. In the book's assumed 10,000-tonne product cargo, why does contribution turn negative when the sale price falls $20 per tonne?
  • A. Because the 0.3% quantity difference is a normal loss allowance
  • B. Because the exchange rate moves from ₦1,500 to ₦1,650
  • C. Because the $199,400 revenue fall on 9,970 saleable tonnes exceeds the $177,050 contribution
  • D. Because financing cost rises with the price fall
C. Because the $199,400 revenue fall on 9,970 saleable tonnes exceeds the $177,050 contribution — 9,970 tonnes × $20 is $199,400, which exceeds $177,050, leaving negative $22,350. The 0.3% is a commercial sensitivity, not a normal loss allowance, and the currency example is a separate illustration.
2. A fictional distributor's optimiser proposes more volume to a higher-contribution customer by relaxing a tank-compatibility restriction that the operations team classifies as a safety condition. What should the commercial director do?
  • A. Reject the plan: a safety restriction is mandatory and cannot be traded against contribution
  • B. Accept it within authority, because contribution rises
  • C. Give the restriction a penalty cost and rerun the solver
  • D. Ask for a better demand forecast
A. Reject the plan: a safety restriction is mandatory and cannot be traded against contribution — A safety restriction cannot become a soft preference because the solver otherwise fails. The penalty-cost route is the tempting one, but an unauthorised activity is not made acceptable by assigning it a financial penalty in the optimiser.
3. A demand model trained on depot sales shows near-zero demand in weeks when the depot had no product. What is the right reading?
  • A. Customer need was zero in those weeks
  • B. Prices were too high in those weeks
  • C. Those weeks should be quietly removed
  • D. Sales during stockouts are a censored view of demand; use availability flags and lost-sales records where reliable
D. Sales during stockouts are a censored view of demand; use availability flags and lost-sales records where reliable — Treating zero sales during closure as zero need biases replenishment. Quietly removing the weeks hides the problem instead of disclosing demand that cannot be observed.

Today’s Assignment

Write Section 8 of your plan: the delivered margin of your Session 1 decision, its funding currency and the constraints that govern your available stock or capacity.
  • Build the delivered margin for your decision in your company on a complete cost boundary and a saleable-quantity basis, or the nearest equivalent economic unit your business uses. Label every figure assumed, or give structure and size without confidential prices.
  • Show the funding-currency exposure: what is already funded or hedged, what remains open and when receipts arrive.
  • Present expected contribution, downside contribution, peak funding and unresolved conditions together, with the declined alternative and the reason.
  • Classify the constraints on your available stock or capacity as mandatory, contractual, operational or discretionary, and say which one your current planning treats as softer than it is.
  • Name the difficult day you would replay.
  • The honest part: where your company reports a quoted spread or a closing-rate translation as trading performance. If no AI is in use yet, that is normal; the first need may be a margin engine, not a margin predictor. Aim for 400 to 900 words.
YOUR 90-DAY PLAN

Section 8 — The delivered margin, its funding currency and the constraints that govern available stock.

How this is marked — the rubric
Builds the margin on saleable quantity and a complete cost boundary, figures labelled assumed30
Shows the funding-currency exposure, what is fixed and when receipts arrive20
Presents expected, downside, peak funding and unresolved conditions with the declined alternative20
Classifies stock or capacity constraints into the four classes, names a replay day and gives an honest example30
Total · pass mark 70100
Submitting session 8
Write your answer in Word or Google Docs. The first line must read Session: 8, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
ASSESSMENT NOW OPEN

Pop Quiz 2 — Contracts, Crude Pricing and the Delivered Margin opens now. Sit it before you start the next session — it is how you find out whether the doctrine landed, and the practice papers may be resat as often as you like.

5 questions · 10 minutes · covers Sessions 6–8 · pass mark 70
Sit Pop Quiz 2 →Closed book, no notes, and Coach Ritchie switches himself off while you sit it.
Capabilities Covered
Delivered marginFunding-currency exposureCensored demandConstraint classificationPredict-then-optimise replay
Tick it once you have submitted.Next: Session 9 →
Part Four · Gas and Physical ExecutionSESSION 9
Gas on an Energy Basis and LNG and LPG Portfolios
Session 9 of 15 · 25-Minute Module

Why This Matters

Where a contract prices gas by energy, volume alone is insufficient, and the chain from nomination through delivery and billing to collected value must reconcile. LNG and LPG cargos add timing, quantity basis and destination rights that a spreadsheet can make look freer than they are. If your business trades crude or products, the lesson transfers: your quantity basis also needs evidence, and every option in your plan needs a right behind it. A model should not invent a right to redirect committed gas, or invent pipeline capacity. By the end you will know your accepted quantity basis, the statuses your records must keep, and which of your options are real.

25-Minute Module
5:00 – 10:00
A bounded energy calculation
  • Fictional accepted delivery recordAccepted factor 0.036Accepted factor 0.034
    Stated volume1,000,000 standard cubic metres1,000,000 standard cubic metres
    Energy36,000 MMBtu34,000 MMBtu
    Gross value at an assumed $4 per MMBtu$144,000$136,000
    Difference$8,000No change in stated volume
  • The factor, in MMBtu per standard cubic metre, is a teaching input, not a conversion standard for every gas stream. The real calculation requires the contract, composition or accepted calorific evidence and correct unit treatment.
  • IN THE PHYSICAL VIEW · THE WORKED CASE
    • Physical view. A fictional gas aggregator's delivery point records volume reliably, but the accepted heating value for the month is still pending. The record should show it as pending, not fill the cell with last month's figure.
    IN THE COMMERCIAL, RISK AND CASH VIEWS · THE PARALLEL
    • Commercial, risk and cash. The invoice, receivable and contribution all depend on that pending value; at the book's assumed numbers, two factors produce an $8,000 difference on one delivery. An energy-content correction and a physical loss are different causes with different financial consequences, and the commercial review must say which it is.
When the volumes agree and the values do not, look at the factor first.
15:00 – 21:00
LNG and LPG: the real cargo rights
  • A gas cargo portfolio needs product, loading and receiving windows, delivery point, accepted quantity basis, quality, transport, storage, destination rights and payment terms. Diversion or cancellation is possible only within the actual rights and constraints; a model cannot treat every destination as a free commercial choice.
  • GIIGNL's Custody Transfer Handbook, sixth edition, identifies its 2021 best-practice basis for LNG custody transfer. Use the accepted applicable edition, contract and measurement procedure for real work. Citing that edition is a historical reference, not an assertion that no later edition exists.
  • LNG economics often require an accepted energy determination; LPG trading may use mass with composition and quality conditions. A nominal vessel capacity does not establish accepted delivered quantity. Keep loaded, transported, received and invoiced states distinct.
  • The book's LNG teaching cargo: 3 million MMBtu of accepted saleable energy at an assumed $9 per MMBtu, against $8.60 of allocated costs, gives $1.2 million contribution before excluded items. A separate $300,000 delay and funding sensitivity reduces it to $900,000. Neither the energy nor the prices describe a real cargo.
  • A receiving outage may delay discharge and reduce downstream sales at once. Build joint scenarios rather than sampling every input independently. For LPG, forecast dispatch can create space in a planning scenario; confirmed capacity needs the actual receiving assessment.
Ask which destination change the agreement actually allows, and by when.
Key Terms

Confirmed nomination

A requested delivery accepted by the transport and receiving parties. It differs from an order and from delivered accepted energy.

Joint scenario

A scenario in which inputs sharing a cause, such as arrival, receiving readiness and demand, move together rather than independently.

Self-Check — Before You Submit
1. Using the book's fictional delivery of 1,000,000 standard cubic metres at an assumed $4 per MMBtu, what changes if the accepted factor is 0.034 rather than 0.036 MMBtu per standard cubic metre?
  • A. Nothing, because the volume is unchanged
  • B. Energy falls by 2,000 MMBtu and value by $8,000
  • C. Value falls by $4,000
  • D. Energy falls by 2%
B. Energy falls by 2,000 MMBtu and value by $8,000 — 36,000 MMBtu becomes 34,000, and $144,000 becomes $136,000. Unchanged volume is the trap: where the contract prices energy, volume alone is insufficient.
2. Why should a nomination model train separate labels for delivery shortfall, customer demand and measurement adjustment?
  • A. So a meter correction is not learned as a demand shock
  • B. Because separate labels always improve pooled accuracy
  • C. Because pooled error is the main measure of a nomination policy
  • D. Because heating values are always measured, never estimated
A. So a meter correction is not learned as a demand shock — Different causes need different labels. Pooled error is the tempting measure, but the book evaluates imbalance cost, unserved energy and peak funding, and warns that a low pooled error can hide repeated failure on the largest customer.
3. A portfolio model gives a fictional LNG cargo a large option value from diverting to a second destination. The sale agreement does not permit that destination. What should the commercial director conclude?
  • A. Book the option value in the plan
  • B. Use the diversion as the base case
  • C. Halve the option value and proceed
  • D. Treat it as an analytical error, at most a commercial-development hypothesis, not an executable improvement
D. Treat it as an analytical error, at most a commercial-development hypothesis, not an executable improvement — Diversion is possible only within the actual rights. Discounting the value is tempting but still counts an option the company does not hold.

Today’s Assignment

Write Section 9 of your plan: the accepted quantity basis of your Session 1 decision, its order-to-cash reconciliation and every option tied to a right.
  • State the accepted quantity basis of your decision in your company (energy, mass or volume, with its reference conditions) and the evidence any conversion needs.
  • Separate the statuses your records must keep: for gas, order, confirmed nomination, delivered accepted energy, billed and collected; for crude or products, the nearest equivalents.
  • Reconcile one month or one cargo of that chain and explain the differences by timing, measurement, contractual flexibility or unresolved evidence, or say plainly why you cannot yet.
  • List every optional action your plan assumes, with the contractual or operational right that permits it and its latest decision time. Mark any option with no right behind it.
  • The honest part: where your company has filled a missing heating value, quality or quantity with a convenient figure, or counted an option it did not hold. Describe structure; no confidential terms or counterparty names. If no AI is in use yet, that is normal; the first useful tool may be an exception detector. Aim for 400 to 900 words.
YOUR 90-DAY PLAN

Section 9 — Our accepted quantity basis, the order-to-cash reconciliation and every option tied to a right.

How this is marked — the rubric
States the accepted quantity basis and the evidence any conversion needs20
Separates the record statuses from order or nomination to collected value25
Reconciles one month or cargo with differences explained, or states why not25
Ties every assumed option to a right and a latest decision time, with an honest example30
Total · pass mark 70100
Submitting session 9
Write your answer in Word or Google Docs. The first line must read Session: 9, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
Capabilities Covered
Energy-basis disciplineNomination status controlOrder-to-cash reconciliationOption rights reviewJoint scenario planning
Tick it once you have submitted.Next: Session 10 →
Part Four · Gas and Physical ExecutionSESSION 10
Freight, Arrival, Demurrage and Custody Transfer
Session 10 of 15 · 25-Minute Module

Why This Matters

Every trade in this programme eventually meets a voyage and a measurement. Vessels arrive late, notices are disputed, and the quantity received differs from the quantity loaded. Those moments decide whether money is paid out, recovered in a claim or written off without a reason. A variance is a question before it is a loss. Today you treat the voyage clock as commercial evidence, weigh a delay intervention on the evidence for its probabilities, and build a reconciled cut-off that counts a consequence once and accuses no one on the strength of a score. Practice Exam 2 closes the week.

25-Minute Module
5:00 – 10:00
A delay decision on evidence
  • Expected value weighs each possible cost by its probability. Here it asks whether paying to reduce the chance of a delay is worth more than it costs. Every input below is fictional: an avoidable delay costing $40,000 a day for three days under accepted applicable terms, and a $30,000 intervention that cuts the delay probability to 0.20.
  • Fictional delay caseBaseline probability 0.60Baseline probability 0.35
    Expected delay cost without intervention0.60 × $120,000 = $72,0000.35 × $120,000 = $42,000
    Expected delay cost with intervention0.20 × $120,000 = $24,0000.20 × $120,000 = $24,000
    Expected avoided cost$48,000$18,000
    Expected net benefit after $30,000$18,000Negative $12,000
  • The same intervention moves from worthwhile to loss-making when one probability changes. The recommendation depends on evidence supporting the probabilities, and should not present the first result as a guaranteed saving.
  • Ask where the baseline probability came from and how it was checked. If nobody can answer, show the committee both columns.
When an intervention pays only at one probability, the probability is the decision.
14:00 – 20:00
A variance is a question before it is a loss
  • Quantity differences can reflect measurement basis, timing, temperature, density, water, permitted adjustments or unresolved physical discrepancy. API's Petroleum Measurement 2024 catalogue covers gauging, sampling, temperature, density and quantity calculation; it does not provide the licensed calculation or establish a facility's compliance.
  • Build a reconciled cut-off: opening stock plus accepted receipts less accepted dispatches and approved adjustments, compared with closing stock on the same basis, each adjustment linked to evidence and authority.
  • Fictional custody varianceTonnes
    Loaded, on a stated comparable basis50,000
    Received49,850
    Initial difference, 0.3% of loaded150
    Documented cut-off issue40
    Accepted correction30
    Residual80, a $56,000 valuation sensitivity at an assumed $700 per tonne
  • IN THE PHYSICAL VIEW · THE WORKED CASE
    • Physical view. The 80-tonne residual remains an open question for measurement and operations: basis, timing, temperature, density, water or a physical discrepancy. Investigation may establish that no physical loss occurred, and that is a valid operating result.
    IN THE COMMERCIAL, RISK AND CASH VIEWS · THE PARALLEL
    • Commercial, risk and cash. The $56,000 is a valuation sensitivity, not automatically an accepted loss, recovery or claim. Separate physical recovery from corrected billing and accounting reclassification, so the financial consequence is counted once.
Ask what remains after the explained items, and who accepted each explanation.
Key Terms

Reconciled cut-off

Opening stock plus accepted receipts less accepted dispatches and approved adjustments, compared with closing stock on the same basis, each adjustment linked to evidence and authority.

Anomaly score

A measure of how unusual a residual is. It prioritises evidence review and is never a probability of theft, fraud or physical loss.

Self-Check — Before You Submit
1. In the book's fictional delay case, the baseline delay probability is 0.35 instead of 0.60, and the intervention still reduces it to 0.20. What happens to the $30,000 intervention?
  • A. Its expected net benefit stays $18,000
  • B. Its expected avoided cost rises
  • C. Expected avoided cost falls to $18,000 and the net benefit becomes negative $12,000
  • D. It becomes worthwhile at any cost
C. Expected avoided cost falls to $18,000 and the net benefit becomes negative $12,000 — 0.15 × $120,000 is $18,000 avoided, less $30,000, giving negative $12,000. Keeping the $18,000 figure is the trap: the recommendation depends on evidence for the probabilities.
2. An anomaly model scores a fictional depot's monthly residual as highly unusual. What should the head of operations do?
  • A. Prioritise the case for evidence review against the reconciled balance, without accusation or write-off
  • B. Suspend the depot team pending investigation
  • C. Write off the residual and close the month
  • D. Report the residual as a confirmed loss
A. Prioritise the case for evidence review against the reconciled balance, without accusation or write-off — An anomaly score is not a probability of theft, fraud or physical loss, and investigation may show no physical loss occurred. Writing off or treating the score as proof skips the question the variance raises.
3. A vessel's position feed goes silent for a day before arrival. What does that establish on its own?
  • A. A compliance concern requiring escalation as misconduct
  • B. Nothing conclusive: a gap can arise for several reasons and should not alone determine commercial or compliance conclusions
  • C. That laytime has started
  • D. That the vessel will arrive late
B. Nothing conclusive: a gap can arise for several reasons and should not alone determine commercial or compliance conclusions — Feed gaps have several possible causes. Treating the gap as a finding is the tempting error; the advisory should show feed age and coverage and leave conclusions to evidence.

Today’s Assignment

Write Section 10 of your plan: the voyage clock, the delay decision and the reconciled cut-off behind your Session 1 decision.
  • Review the last five material delays or variances that touched your decision in your company, and classify each avoidable cause: late information, unavailable resources, unresolved authority or an unavoidable condition.
  • Set out the reviewed chronology (notices, events, accepted times, exclusions and claims deadlines) or the reconciled cut-off your decision needs, and who accepts each entry by role.
  • Show, on inputs labelled fictional or assumed, how an expected-value delay or variance decision would depend on evidence for its probabilities, and where that evidence would come from.
  • Separate physical recovery, corrected billing and accounting reclassification so the consequence is counted once, and record claims raised, disputed, accepted and collected separately.
  • State how any anomaly score would be used, and the rule that prevents it becoming an accusation or a write-off.
  • The honest part: where your company has booked a claim as revenue, or treated a variance as a loss before investigating it. Do not name counterparties, vessels, terminals or staff. If no AI is in use yet, that is normal; the first need may be deterministic reconciliation. Aim for 400 to 900 words.
YOUR 90-DAY PLAN

Section 10 — The voyage clock, the delay decision and the reconciled cut-off behind our decision.

How this is marked — the rubric
Classifies five real delays or variances by avoidable cause25
Sets out the chronology or reconciled cut-off with acceptance by role25
Shows how the expected-value decision depends on evidenced probabilities, inputs labelled25
Separates recovery, billing and reclassification, bars accusation and write-off, and gives an honest example25
Total · pass mark 70100
Submitting session 10
Write your answer in Word or Google Docs. The first line must read Session: 10, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
ASSESSMENT NOW OPEN

Practice Exam 2 — Crude, Products, Gas and Physical Execution opens now. Sit it before you start the next session — it is how you find out whether the doctrine landed, and the practice papers may be resat as often as you like.

15 questions · 25 minutes · covers Sessions 1–10 · pass mark 70
Sit Practice Exam 2 →Closed book, no notes, and Coach Ritchie switches himself off while you sit it.
Capabilities Covered
Voyage chronologyEvidence-based delay decisionsClaims controlReconciled cut-offsAnomaly review without accusation