30-Session Programme · 25 Minutes Per Day · Free · For leaders in Nigeria’s engineering, procurement and construction sector
WEEK 6 OF 6 · THE AUTHOR'S PRACTICES AND THE NINETY DAYS · SESSIONS 26–30 · WORK AT YOUR OWN PACE
This week’s assessments: Pop Quiz 6 — The Author's Three Practices after Session 28 · Practice Exam 6 — Full Syllabus after Session 29 · Final Exam in Session 30
By Session 30: you hold a signed 90-Day Intelligent EPC Programme for your own company · Every assignment marked against a published rubric · Pass mark 70
Part Six · Capital and the Leadership ExecutionSESSION 26
Daily Portal Monitoring and Commercial Readiness
Session 26 of 30 · 25-Minute Module

Why This Matters

This week turns to three practices I put into operation myself, and today is the first: daily portal monitoring. I describe it only as the book does, with no invented win rate, saving or revenue attached. It matters to you for a plain reason. A tender notice creates work before anyone writes a bid, and a certification or permit issue can decide whether your company can pursue or execute that work at all. If the information reaches business development alone, Operations discovers the implications after the commitment is made. Today you design a monitoring practice with a source basis, a digest your people can act on and a recorded link from each item to a decision. That is Section 26 of your programme.

25-Minute Module
4:00 – 10:00
A source basis, not a hopeful search
  • Keep a register of authorised sources: portal, purpose, access basis, update frequency, content type, accountable owner and fallback. An automated check should not bypass authentication, and a failed access attempt is not evidence that no new notice exists. Do not depend on an assumed scraping capability.
  • AI belongs in interpretation and routing. Collection, access checks, dates, identities and distribution should be engineered as dependable functions. The proposed sequence is collection, identity and change detection, extraction, requirement interpretation, capability comparison, review and distribution, with success recorded at each stage. An ambiguous date or a local time without a clear zone goes back for confirmation.
  • A content hash is a fingerprint calculated from a file; change the file and the fingerprint changes. It identifies changed bytes, not commercial significance. Reformatting changes a hash without changing the requirement, while a revised deadline buried in an attachment matters. Pair it with a reviewed comparison of material fields and keep the previous version.
  • Record elementStored valueOperational purpose
    Notice identitySource and published identifier or accepted internal keyDistinguish repeat notifications from new opportunities
    Retrieval stateCollection time and stage outcomesEstablish what the service actually checked
    Source versionOriginal record and permitted attachment referencesReconstruct the basis of the digest
    Extracted requirementProposed value, source location and review statePreserve interpretation and its supporting content
    Next actionProposed owner, deadline and review dispositionConnect the notice to accountable work
  • THE DOCTRINE

    A silent empty digest can mean no relevant changes, or a broken monitoring process. Those are different operating states.

Ask which source failed last week. If nobody knows, build the coverage statement first.
15:00 – 21:00
The worked digest and notice N-014
  • The book's worked digest is hypothetical. Twelve registered sources are due; eleven are collected and one needs manual follow-up because access failed. Coverage is 11/12, or 91.67%. That is not tender detection recall, the share of all relevant notices actually found: nobody knows what the inaccessible source contains.
  • AT THE WORKFRONT · THE WORKED CASE
    • Workfront. In the hypothetical walkthrough, notice N-014 sets a submission deadline on day twelve of the teaching tender period and requires equipment information; an amendment changes the request. Both versions are kept under one identity. The AI summary proposes a match to the utility-package capability profile, citing passages, but flags incomplete supplier-package evidence and an unresolved qualification condition.
    IN THE COMMITMENT · THE PARALLEL
    • Commitment. The managing director asks whether the company can close the missing evidence in time and carry the commitment; a relevance ranking does not answer it. The pursue decision records the preparation owner and latest review point. If evidence stays absent, the bid owner seeks clarification, proposes a permissible qualification or recommends withdrawal.
  • Follow each item into its decision: acknowledgement, relevance, eligibility review, pursue or decline with a reason, submission and outcome. Track missed notices, incorrect flags, unacknowledged actions and source failures.
  • THE DOCTRINE

    A digest can improve visibility. A bid can improve access to work. Actual margin and cash depend on execution and collection. Do not combine these stages into an unsupported claim that monitoring produced profit.

  • If BD holds many acknowledged notices without decisions, the constraint may be management capacity rather than detection. If Operations repeatedly finds missing evidence late, change the routing point.
An entirely green digest should make you more curious, not less.
Key Terms

Coverage statement

Which sources were checked successfully, which failed and which need manual follow-up. It is not detection recall.

Content hash

A file fingerprint that shows something changed, not whether the change matters commercially.

Self-Check — Before You Submit
1. Your digest reports source collection coverage of 11/12, or 91.67%. What may your BD director conclude?
  • A. The service detected about 92% of relevant tenders
  • B. Eleven of twelve sources were collected; the inaccessible source's contents are unknown
  • C. The digest is complete because the shortfall is small
  • D. Detection recall is at least 91.67%
B. Eleven of twelve sources were collected; the inaccessible source's contents are unknown — The figure measures collection coverage only. Reading it as tender detection recall is the trap: nobody knows what notices the inaccessible source holds.
2. A fictional EPC contractor's digest flags a notice. A certificate's title contains a similar word but its scope is unclear. The BD manager wants it shown as eligible so work starts today. What do you instruct?
  • A. Show eligible, since the deadline is close
  • B. Drop the notice until the certificate is renewed
  • C. Show the uncertainty and route applicability to the responsible review with an owner
  • D. Rerank with a higher similarity threshold
C. Show the uncertainty and route applicability to the responsible review with an owner — A similar title is not proof of qualification. Dropping the notice loses a possible opportunity; marking it eligible claims what the evidence does not support.
3. The email system confirms the digest reached every recipient on time. What does that establish?
  • A. That the notices were reviewed
  • B. That readiness was assessed
  • C. That monitoring is working
  • D. Transmission only; dispositions must still be collected
D. Transmission only; dispositions must still be collected — Appendix H says not to equate a delivery receipt with a completed review. A digest can also arrive on time from a broken monitoring process.

Today’s Assignment

Write Section 26 of your programme: a monitoring practice for the commitments or opportunities your company depends on, with a source basis, an actionable digest and a link from digest to decision.
  • List the sources for your decision chain with access basis, update frequency, owner and fallback. Say honestly how your business monitors them today and what it misses.
  • Define the record for each item using the book's five elements, and lay out the digest in Appendix H's four sections with a coverage statement.
  • Show how an item becomes a recorded pursue, decline or hold decision, and name who resolves competing opportunities and funds readiness work.
  • State what AI does, what stays deterministic or manual, and the measures you will track.
YOUR 90-DAY PLAN

Section 26 — Monitoring with a source basis and a digest that leads to decisions.

How this is marked — the rubric
Source register specific to your company, with owner, fallback and honest gaps25
Record and digest follow the book's elements and Appendix H, with coverage statement25
Digest-to-decision link names the roles that assess, decide and fund30
AI and deterministic functions separated; measures make no profit claim20
Total · pass mark 70100
Submitting session 26
Write your answer in Word or Google Docs. The first line must read Session: 26, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
Capabilities Covered
Source disciplineCoverage reportingCapability matchingActionable digestsDigest-to-decision tracking
Tick it once you have submitted.Next: Session 27 →
Part Six · Capital and the Leadership ExecutionSESSION 27
PSR Discipline, Completeness and Coaching
Session 27 of 30 · 25-Minute Module

Why This Matters

Yesterday's practice brought external information into the company. Today's brings internal reporting into management. I put a PSR discipline in place using Project and Personal Status Reports, with AI engines reviewing them for completeness and supporting coaching of the team. Most leaders have read a status report that was complete in every heading and still gave them nothing to act on. The uncomfortable part of this session is that the fault is not always the writer's: a reported approval that stays undecided points back at management. Today you set the accepted structure of your reports, define completeness beyond a filled heading, and decide how the review coaches the action and connects repeated findings with support. That is Section 27.

25-Minute Module
4:00 – 10:00
An accepted structure and real completeness
  • Define sections, rhythm, reporting period, source cut-off and owner, adapted to the role. Green without evidence is not a supported position; amber or red should identify consequence, action and responsible decision.
  • Element (Appendix I)What the review looks for
    Action itemsSpecific action, owner, due date and closure evidence
    Current tasksScope, status, next step and relevant commitment
    Completed tasksResult and accepted evidence
    Risks and issuesEvent or existing condition, consequence, response and owner
    DependenciesNeeded input, responsible party and latest useful date
    ResourcesRequirement, operational consequence and decision requested
    CoachingSpecific improvement, support and follow-up
  • Appendix I, the PSR completeness and coaching rubric, records five distinct outcomes: applicable, not applicable with accepted reason, missing, unsupported and requires clarification.
  • THE DOCTRINE

    Separate structural completeness from factual truth. A report can fill every field and still be inaccurate.

  • The finding taxonomy: missing section, missing owner, missing date, unsupported completion, inconsistent status, unresolved dependency, unclear resource request and insufficient coaching action. Avoid a single score that conceals material defects: an unsupported critical completion claim needs attention even if the average is high.
A filled heading is a structural fact. Whether the work happened is a different question.
15:00 – 21:00
Coach the action, then find the management dependency
  • Add more detail is weak coaching. Better coaching names the missing decision relationship: identify the supplier commitment, show the required-on-site date, state which system milestone is affected. A manager reviews sensitive or consequential coaching, and the engine must not infer attitude, competence or motive from sparse reporting.
  • AT THE WORKFRONT · THE WORKED CASE
    • Workfront. In the walkthrough's hypothetical week-eight report, P-01 is green and W-01 is ready, while a pending operating interface is also reported. The engine flags the inconsistency, citing the report and the R-03 interface record, and asks the reporter to separate equipment progress, installation readiness and forecast completion. The supervisor corrects the status and keeps the original.
    IN THE COMMITMENT · THE PARALLEL
    • Commitment. The management brief shows the unresolved client coordination decision, owned by the project director with the authorised client counterpart. Rewriting the PSR cannot remove that constraint. A complete revised PSR is one result; an accepted interface date and an executable installation package are separate results.
  • THE DOCTRINE

    If an employee repeatedly identifies a required approval and the approval remains undecided, coaching the employee to improve their wording will not close the loop.

  • Treat recurring findings as hypotheses: the pattern alone does not establish the cause. Repeated requests for one approval can suggest an unresolved decision; repeated missing references, poor repository access. After asking the relevant owners, the executive can assign an approval owner, repair access, change the reporting guidance or resolve funding.
  • Evaluate against supervisors' reference findings. Precision asks how many raised findings were real; recall, how many real issues were found. Test coaching separately for factual support and inappropriate personal inference.
Coach the person on the report. Coach yourself on the decisions the reports keep asking for.
Key Terms

Structural completeness

Required elements present or justifiably not applicable. It does not establish accuracy or acceptance.

Management dependency

A reported constraint that only a management decision can close, such as an approval left undecided.

Self-Check — Before You Submit
1. A well-formatted report has a high average score but an unsupported completion claim on a critical item. How is it treated?
  • A. Accepted on its average
  • B. Returned for plainer prose
  • C. Flagged with the critical exception visible and routed for review
  • D. Marked red for the whole project
C. Flagged with the critical exception visible and routed for review — A total score must not conceal an unsupported critical completion statement. Rewriting the prose is the trap: it does not establish whether the work was done.
2. In a fictional fabrication subcontractor, four reporters across three periods record the same inspection approval as still awaited. A manager proposes coaching their wording. What do you do?
  • A. Treat the pattern as a possible unresolved management decision, investigate it with the owners and decide the approval or funding
  • B. Coach all four on wording
  • C. Remove the item from templates
  • D. Score the four lower
A. Treat the pattern as a possible unresolved management decision, investigate it with the owners and decide the approval or funding — Repeated requests for one approval can suggest an unresolved decision, a hypothesis the executive investigates and then acts on. Coaching wording will not close that loop, and penalising staff turns the service into surveillance.
3. The AI review fails on submission day and an on-time report shows as missing. What is correct?
  • A. Record it as late
  • B. Wait for the service before reviewing
  • C. Ask for resubmission
  • D. Preserve the submission, continue supervisor review and log the incident separately
D. Preserve the submission, continue supervisor review and log the incident separately — A failed AI run should not make an on-time report appear missing. Waiting treats the AI layer as the record; the submitted report is the author's record.

Today’s Assignment

Write Section 27 of your programme: the accepted structure of your company's status report, completeness beyond filled headings, and how review coaches the action and routes repeated findings.
  • Set the structure for one report used on your decision chain: sections, rhythm, cut-off, owner and not-applicable rules.
  • Define completeness element by element using Appendix I's five outcomes. Say honestly where reports in your business look complete but are not.
  • Give your RAG meanings and one coaching example that names the missing decision relationship.
  • Name the recurring dependency in your company you suspect is a management decision, who decides it, and your protections for personal findings and AI failure.
YOUR 90-DAY PLAN

Section 27 — The report structure, real completeness and coaching the action.

How this is marked — the rubric
Structure specific to a real report in your company, with cut-off, owner and not-applicable rules20
Completeness defined with Appendix I outcomes, separating omission, evidence gap and operating problem30
Coaching example names the decision relationship without personal inference20
Repeated findings routed to a named management owner, with access and failure protections30
Total · pass mark 70100
Submitting session 27
Write your answer in Word or Google Docs. The first line must read Session: 27, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
Capabilities Covered
Report structureCompleteness reviewAction coachingManagement follow-upFair review governance
Tick it once you have submitted.Next: Session 28 →
Part Six · Capital and the Leadership ExecutionSESSION 28
Quote Preparation and Commercial Completeness
Session 28 of 30 · 25-Minute Module

Why This Matters

A quotation commits your company to far more than a headline rate. It can define scope, measurement, technical basis, materials, equipment, mobilisation, exclusions, schedule, payment and acceptance, and a missing assumption can become an execution obligation after award. I used AI in reviewing and creating quotes to help ensure that requirements and cost elements were not missed. That phrase states an operating objective, not a guarantee of zero omissions. Today you make the commitment visible before it is priced, keep the arithmetic deterministic and let AI draft only from an approved basis. That is Section 28, and Pop Quiz 6 opens at the end.

25-Minute Module
4:00 – 10:00
The requirement-to-quote matrix
  • Freeze a controlled enquiry set for each quote version: enquiry, attachments, accepted clarifications, specifications and commercial instructions. A later email triggers a new comparison, not a silent edit.
  • Break the enquiry into atomic requirements, each specific enough to map to one response and its evidence, linked to the parent clause. For each, record source location, deliverable, quantity and unit, technical basis, responsibility, response, pricing line, qualification and reviewer. Do not normalise area and volume to one unit without competent agreement.
  • Classify each as covered, qualified, excluded, unclear or legitimately not applicable. A material unclear item stays an open commercial decision with a named authority, and every material qualification must appear in the final offer.
  • Requirement recordInternal connectionExternal response connection
    Required scope and quantityCost line and measurement basisStated included scope and quote line
    Material responsibilitySupplier or client basis and related costExplicit responsibility in the offer
    Technical acceptanceAccepted method and required verification costRelevant qualification or commitment
    Schedule and resourcesFeasible mobilisation and delivery assumptionProposed duration and dependencies
    Payment and validityFunding assessment and rate-validity basisReviewed commercial terms
If you cannot point to the line that prices a requirement, it is not covered.
16:00 – 21:00
AI drafts from the approved basis; the quote carries into delivery
  • The drafting service receives the controlled matrix, reviewed pricing model and accepted qualifications. It must not invent resources, warranties, delivery commitments, a supplier offer or available equipment.
  • Compare in both directions: does every requirement have a response, and does every material promise have an approved basis? The second catches invented warranties and unapproved commitments.
  • AT THE WORKFRONT · THE WORKED CASE
    • Workfront. In the book's hypothetical surface-preparation example, the consumption basis is unsettled: 40 or 50 kg/m². The assistant shows both values and the ₦48 million consequence instead of picking one.
    IN THE COMMITMENT · THE PARALLEL
    • Commitment. Commercial leadership decides how that risk enters the offer. A negotiated five-percent discount takes the margin from 21.875% to about 17.76% on the unchanged provision; a discount that also transfers material responsibility back to the client is a different offer.
  • THE DOCTRINE

    A second AI prompt can propose additional checks, but agreement between two prompts does not establish independent assurance. Shared source omissions can survive both reviews.

  • Include an enquiry that cannot be priced from the evidence; an engine that completes the quote anyway has failed the control. At award, reconcile the executed agreement with the final offer, and keep scope changes separate from estimating errors.
Measure omissions found before submission, not the number of quotes generated.
Key Terms

Atomic requirement

A requirement specific enough to map to one response and its evidence, linked to its parent clause.

Pricing-model margin

Price less cost provision, divided by price. It is not accounting profit.

Self-Check — Before You Submit
1. In the book's teaching example, 600 tonnes rise from ₦400,000 to ₦450,000 per tonne over 12,000 m². What is the effect?
  • A. ₦48 million
  • B. ₦30 million, or ₦2,500 per m² before margin
  • C. ₦30 million, or ₦4,000 per m²
  • D. ₦24 million, or ₦2,000 per m²
B. ₦30 million, or ₦2,500 per m² before margin — 600 × ₦50,000 = ₦30 million; ÷ 12,000 m² = ₦2,500. ₦48 million is the trap: it is the consumption sensitivity, not the price one.
2. A fictional EPC contractor's AI draft covers every matrix requirement but adds a warranty found nowhere in the approved basis. The deadline is tomorrow. What do you do?
  • A. Submit; coverage is complete
  • B. Ask a second prompt to confirm it
  • C. Remove the warranty or route it through authorised approval
  • D. Add a contingency line
C. Remove the warranty or route it through authorised approval — The second direction asks whether every promise has an approved basis. Agreement between two prompts is not independent assurance.
3. Price ₦160 million, provision ₦125 million, five-percent discount, scope unchanged. Margin?
  • A. About 17.76% of sales
  • B. 16.875%
  • C. 21.875%
  • D. About 22.0%
A. About 17.76% of sales — Price ₦152 million less ₦125 million is ₦27 million, about 17.76%. Subtracting five points to reach 16.875% is the trap; recalculate from the new price.

Today’s Assignment

Write Section 28 of your programme: make one commitment your company prices visible before it is priced, build its requirement-to-quote matrix and show complete pricing.
  • Choose a real enquiry or offer on your decision chain; freeze its controlled enquiry set and list what is missing or disputed.
  • Build the matrix for at least ten atomic requirements, each classified covered, qualified, excluded, unclear or not applicable.
  • Show your most sensitive assumption by deterministic calculation and name its owner. Say honestly what your company has omitted or double counted before.
  • State how AI drafts only from the approved basis and who approves technically, commercially and financially.
YOUR 90-DAY PLAN

Section 28 — The visible commitment, the requirement-to-quote matrix and complete pricing.

How this is marked — the rubric
Enquiry set and atomic requirements specific to a real commitment, with gaps recorded25
Classifications justified; unclear items held as open decisions under a named authority25
Sensitive assumption calculated correctly with its owner; complete-delivery check honest30
Drafting bounded to the approved basis, with two-direction comparison and separate approvals20
Total · pass mark 70100
Submitting session 28
Write your answer in Word or Google Docs. The first line must read Session: 28, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
ASSESSMENT NOW OPEN

Pop Quiz 6 — The Author's Three Practices opens now. Sit it before you start the next session — it is how you find out whether the doctrine landed, and the practice papers may be resat as often as you like.

5 questions · 10 minutes · covers Sessions 26–28 · pass mark 70
Sit Pop Quiz 6 →Closed book, no notes, and Coach Ritchie switches himself off while you sit it.
Capabilities Covered
Commitment visibilityRequirement mappingDeterministic pricingComplete delivery costingBounded drafting
Tick it once you have submitted.Next: Session 29 →
Part Six · Capital and the Leadership ExecutionSESSION 29
The Intelligent Project Review
Session 29 of 30 · 25-Minute Module

Why This Matters

Every practice so far ends in a meeting where someone must decide. If that meeting reviews a single percentage, a colour averaged across unrelated conditions and a brief nobody checked against its sources, the earlier discipline is wasted. Today is the intelligent project review: one integrated position that keeps engineering, material, execution, quality, acceptance and cash distinct while showing their dependencies; a weekly rhythm; RAG with operational meaning; an AI-prepared brief the project director has actually checked; and a scorecard that leads to decisions. You will also recompute Casebook Case 10, where a delay changes the investment horizon. That is Section 29, and Practice Exam 6 opens at the end.

25-Minute Module
4:00 – 9:00
A proposed weekly rhythm and RAG that means something
  • StageThe book's proposed rhythm
    BeforeSource owners accept the cut-off and reconcile discrepancies. Planning evaluates milestone consequences; commercial assesses notices and changes; finance updates funding and estimate-to-complete exposure. The project director selects cross-functional decisions.
    DuringDecide the action and conditions. Record dissent where it matters. Assign resources and a review date.
    AfterThe owner executes or reports why not. Closure is verified with evidence and examined at the next review.
  • An action phrased as monitor progress is incomplete unless it names what observation will trigger which decision.
  • Proposed RAG, to adapt for the particular commitment: red, an unresolved condition that prevents the accepted plan or requires executive action; amber, exposure with an owner and a feasible response; green, current supporting evidence within the accepted basis. Never average colour across unrelated conditions; a mandatory unresolved test stays visible.
  • THE DOCTRINE

    Report overdue decisions separately from overdue tasks. The latter can reflect execution; the former can reflect management.

Count the overdue decisions on your own desk before anyone's overdue tasks.
15:00 – 21:00
Case 10: the delay that changes the horizon
  • Plain terms first: money that arrives later is worth less today. Net present value (NPV) converts each future amount to today's value and subtracts the upfront cost. At the assumed 20%, ₦30 million at the end of year one is worth ₦30 million ÷ 1.2, or ₦25 million.
  • The book's assumed inputs: upfront cost ₦60 million; gross supported benefit ₦45 million a year; operating and response cost ₦15 million; net ₦30 million; three years; benefits at year-end; no terminal value, tax or inflation adjustment.
  • ScenarioCalculationResult
    Base case₦25m + ₦20.833m + ₦17.361m = ₦63.194m, less ₦60mNPV about +₦3.194 million; simple payback two years
    One-year delay shifts all three benefits₦63.194m ÷ 1.2 = ₦52.662m, less ₦60mNPV about −₦7.338 million
    Fixed three-year horizon, year one lost−₦60m + ₦30m/1.2² + ₦30m/1.2³NPV about −₦21.806 million
    60% of gross benefit realised₦45m × 60% − ₦15m = ₦12m a yearNPV about −₦34.722 million
  • THE DOCTRINE

    Realised benefit assumptions dominate the case more than a modest software price discount. A financially elegant spreadsheet cannot make an unsupported benefit real.

  • The fixed-horizon case is a different scenario, not a timing shift. The inputs are hypothetical and the rate is not a Nigerian corporate financing recommendation; finance sets the real basis. The walkthrough likewise shows how issues could be exposed but quantifies no savings and does not prove AI improved the outcome.
Before you approve an AI investment, ask what happens if it starts a year late.
Key Terms

RAG with operational meaning

Colours defined for the particular commitment, each tied to evidence, owner or executive action.

Net present value

Future cash flows converted to today's value at a stated rate, less the upfront cost.

Self-Check — Before You Submit
1. In Case 10, a one-year delay shifts all three ₦30 million benefits to years two to four; the ₦60 million is still paid at year zero. NPV at 20%?
  • A. About +₦3.194 million
  • B. About −₦21.806 million
  • C. About −₦7.338 million
  • D. About −₦34.722 million
C. About −₦7.338 million — ₦63.194 million ÷ 1.2 is about ₦52.662 million, giving about −₦7.338 million. −₦21.806 million is the trap: it is the fixed-horizon scenario where year one's benefit is lost.
2. A fictional EPC contractor's package is favourable on six of seven measures; the seventh, a mandatory test, is unresolved. Controls proposes green overall. What do you decide?
  • A. Accept green
  • B. Keep the mandatory test visible on its own under the agreed definitions
  • C. Report amber as a compromise
  • D. Drop the test until resolved
B. Keep the mandatory test visible on its own under the agreed definitions — Colour is never averaged across unrelated conditions. Amber as a compromise is the trap: it still hides the condition that may block the plan.
3. A review action reads: monitor progress on the client interface. What is missing?
  • A. A RAG colour
  • B. A wider distribution
  • C. Nothing
  • D. The observation that triggers which decision, with owner and date
D. The observation that triggers which decision, with owner and date — The book calls such an action incomplete until it names the triggering observation and decision. A colour describes the position but decides nothing.

Today’s Assignment

Write Section 29 of your programme: one integrated position for your company's decision chain, a weekly rhythm, operational RAG, the AI-prepared brief and a decision scorecard.
  • Set out the integrated position for one commitment in your company, evidence states distinct and the next material commitment at the top.
  • Write the before, during and after rhythm with a role for each step, and define red, amber and green for that commitment.
  • List overdue management decisions separately from overdue tasks. Say honestly which decisions in your business are overdue now.
  • Specify the brief and its reviewer, choose four to six measures with owners and thresholds, and state how a one-year delay would change your investment case.
YOUR 90-DAY PLAN

Section 29 — The integrated position, the weekly rhythm and a scorecard that leads to decisions.

How this is marked — the rubric
Integrated position keeps evidence states distinct and opens with the next commitment25
Rhythm and RAG are operational, with overdue decisions separated25
Brief is sourced and reviewed by a named role25
Measures have owners and thresholds; delay effect reasoned correctly25
Total · pass mark 70100
Submitting session 29
Write your answer in Word or Google Docs. The first line must read Session: 29, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
ASSESSMENT NOW OPEN

Practice Exam 6 — Full Syllabus opens now. Sit it before you start the next session — it is how you find out whether the doctrine landed, and the practice papers may be resat as often as you like.

15 questions · 25 minutes · covers Sessions 1–29 · pass mark 70
Sit Practice Exam 6 →Closed book, no notes, and Coach Ritchie switches himself off while you sit it.
Capabilities Covered
Integrated project positionReview rhythmOperational RAGDecision scorecardsInvestment timing
Tick it once you have submitted.Next: Session 30 →
CapstoneSESSION 30
The Executive Commitment: Your Signed 90-Day Intelligent EPC Programme
Session 30 of 30 · 25-Minute Module

Why This Matters

Twenty-nine sessions ago you chose one decision chain with material value, accessible evidence, an accountable owner and a practical response. Since then you have built the business, evidence, method, governance, delivery, assurance, people and funding around it, and this week three practices and the review that holds them together. Today you assemble those twenty-nine sections into one signed 90-Day Intelligent EPC Programme. The ninety days are the book's proposed sequence, not a delivery promise. You use the AI use and pilot charter and the benefits and funding ledger as templates, set your scaling rule, make the executive commitment, and then sit the Final Exam.

25-Minute Module
4:00 – 10:00
The ninety days as the book sets them out
  • Ninety days should establish a maintained capability, not cover the enterprise. If identities or authority are unresolved, their correction joins the programme. A prototype that works only on a curated sample the business cannot maintain has not succeeded.
  • StageWhat the book sets outDecision at the end
    Days one to thirtyMap the decision and current workflow; baseline effort, delays, corrections and outcomes; define population, source cut-off, ownership and permitted authority; reconcile identifiers and essential records; select the simpler comparator and prepare representative and challenging evaluation cases; agree release conditions, incident response and manual fallback; build the economic case with full cost and a downside.Whether enough evidence and operating readiness exist to justify development. Repairing the process before building is a valid outcome.
    Days thirty-one to sixtyBuild the bounded service and test each response stage; investigate errors and retain corrected reference cases; avoid tuning on the protected test set; operate in shadow mode with actual users, measuring reviewer time and whether recommendations arrive while action is possible, and recording cases where no response is feasible; validate support, source updates and recovery.Update the investment case with observed effort; narrow or redesign if specialist attention is excessive.
    Days sixty-one to ninetyPrepare the release argument with evidence, limitations, conditions and owners; authorise only the defined use and authority; train users through practical tasks; establish monitoring, source freshness checks, change control and incident handling; review initial outcomes with finance and the workflow owner, distinguishing technical improvement, changed actions and verified business value.Retain, narrow, improve, withdraw or expand.
  • Shadow operation runs beside the existing process without granting the service its intended consequential authority. The book's twelve-month capability plan, which it calls a proposed roadmap rather than a promised delivery duration, runs this ninety-day process in months one to three, adds one related connection in months four to six and another accepted population in months seven to nine, each of these three stages ending in an investment gate, and consolidates the portfolio in months ten to twelve.
Mark the day-thirty decision honestly. Repairing first is not failing.
15:00 – 20:00
Scaling, the retained advantage and the commitment
  • THE DOCTRINE

    Expansion to another discipline, client, site or document population is a change in use. Assess what transfers and what does not, and evaluate the new population.

  • The strategic asset is the maintained decision capability. A competitor may buy the same model without your requirement library, package relationships, supplier history and review discipline. The book's three horizons (strengthen today's control, connect workflows, develop a new offering) each need their own case.
  • The managing director sponsors the portfolio; workflow owners accept process outcomes; technical authorities, technical use; finance, economic treatment; the service owner maintains configuration, monitoring and recovery. Board measures need defined denominators; counts of users or prompts describe adoption, not delivery.
  • AT THE WORKFRONT · THE WORKED CASE
    • Workfront. A fictional smaller fabrication contractor with weak document identity starts, as the book suggests, with a controlled requirement register and a modest quote completeness review. Its service owner keeps freshness checks and the manual fallback working after day ninety.
    IN THE COMMITMENT · THE PARALLEL
    • Commitment. Its managing director names sponsor and service owner and funds operation after the pilot. Shown incidents and limitations beside results, the sponsor retains the service at its current scope rather than expand early.
A project team that disappears at launch leaves an unsupported dependency. Fund the service owner.
Key Terms

AI use and pilot charter

Appendix B's twelve-item specification of a use, written before building.

Change in use

Expansion to another discipline, client, site or document population, requiring fresh evaluation.

Self-Check — Before You Submit
1. At day thirty a fictional EPC contractor finds tag identities unreconciled. The sponsor wants to build anyway. What does the book support?
  • A. Build now, fix later
  • B. Make the correction part of the programme; repairing before building is valid
  • C. Test on a curated sample
  • D. Widen to the whole enterprise
B. Make the correction part of the programme; repairing before building is valid — Chapter 31 makes unresolved identities part of the programme. The curated sample is the trap: success on a sample the business cannot maintain is not success.
2. A digest service that works for one unit is proposed for a second client's projects. How is that treated?
  • A. As a change in use, with the new population evaluated
  • B. As a configuration update
  • C. As proven by the first gate
  • D. As a new offering
A. As a change in use, with the new population evaluated — Expansion to another client is a change in use. Treating the first gate as proof is the trap; each new population needs its own evaluation.
3. Procurement and scheduling both claim the full avoided delay cost for one recovered package. What does Appendix F require?
  • A. Count both
  • B. Count the larger
  • C. Count neither until close-out
  • D. Identify the overlap so it is not counted twice
D. Identify the overlap so it is not counted twice — Appendix F forbids counting the full avoided delay cost independently twice. Taking the larger still lacks supported attribution; finance accepts the valuation.

Today’s Assignment

Assemble Sections 1 to 29 into one signed 90-Day Intelligent EPC Programme for your company, with a one-page summary your executive team can decide on.
  • Assemble the twenty-nine sections in order, noting where later sessions changed earlier ones.
  • Write the one-page summary: decision chain, owner and authority, and the three ninety-day stages with their closing decisions, labelled as a proposed sequence.
  • Complete the Appendix B charter in all twelve items, saying honestly which your company cannot yet fill.
  • Attach the Appendix F ledger with predicted and actual separate and overlaps identified.
  • State your scaling rule and executive commitment, including the commitment your business is least likely to keep. Sign and date it.
YOUR 90-DAY PLAN

The signed 90-Day Intelligent EPC Programme.

How this is marked — the rubric
Sections assembled, signed and dated, with a summary naming chain, owner and authority20
Ninety days follow the book's three stages with closing decisions25
Charter complete in Appendix B's twelve items, gaps stated honestly20
Ledger follows Appendix F with no double counting20
Scaling rule and commitment name sponsor, service owner, budget and weakest commitment15
Total · pass mark 70100
Submitting session 30
Write your answer in Word or Google Docs. The first line must read Session: 30, or the submission is refused. Upload the Word file (.docx), or switch to the Google Doc tab and paste your document’s share link.
Marked against the rubric above and returned as a written letter, saved to your progress page. Do not submit until you have passed the self-check above.
FINAL EXAM

Your Final Exam is sat in this session. 15 questions, of which 3 are rebuilt from questions you got wrong on the practice papers. Sit it once your capstone is submitted.

15 questions · 30 minutes · covers Sessions 1–30 · pass mark 70
Sit the Final Exam →Closed book, no notes, and Coach Ritchie switches himself off while you sit it.
Capabilities Covered
Programme assemblyPilot charteringBenefit disciplineScaling decisionsExecutive commitment
Tick it once you have submitted.Sit the Final Exam →